3DS-D1 Project,Kyusyu Sekiyu Ohita
Refinery (2)
Ohita Prefecture,Aprile 4,1998
2. Loading onto a trailer
2.1 The Reactor was loaded on self-propelled platform type
trailer with six axles to be carried to the final destination.
3. Transportation to the site.
4.
Erection
4.1 The Reactor was erected by two cranes at very confined
site
with live process lines. The primary lift crane was P&H7450
crawler crane, which lifting capacity was 200-ton, and tail crane
was telescopic type crane of which lifting capacity was 200-ton.