3DS-D1 Project,Kyusyu Sekiyu Ohita Refinery (2)

Ohita Prefecture,Aprile 4,1998

 


          




2. Loading onto a trailer

2.1 The Reactor was loaded on self-propelled platform type

trailer with six axles to be carried to the final destination.















3. Transportation to the site.






















4. Erection
4.1 The Reactor was erected by two cranes at very confined site

with live process lines. The primary lift crane was P&H7450

crawler crane, which lifting capacity was 200-ton, and tail crane

was telescopic type crane of which lifting capacity was 200-ton.